- 04:18 PM Support #139: Confirmation of the analysis to be conducted by the BST
- Ruan Marais wrote:
> The analysis required is
>
> 1) Human RNASeq and downstream analysis as noted specifically ... - 04:14 PM Support #139: Confirmation of the analysis to be conducted by the BST
- The analysis required is
1) Human RNASeq and downstream analysis as noted specifically related to immune system g... - 11:56 AM Support #139 (New): Confirmation of the analysis to be conducted by the BST
Ruan, please confirm that the human component aspect the BST should conduct is the human RNA seq and downstream ana...
02/11/2022
- 01:43 PM Support #138: 10 February 2022 meeting update and way forward
- Thank you Ephie
The folder `/cbio/projects/017` was created for this project. The folder is shared with the necess...
02/10/2022
- 04:02 PM Support #138 (New): 10 February 2022 meeting update and way forward
- Dear Ruan and Gerrit,
The following are the updates on the project:
* 1. Ruan will share the 20 samples that are ...